Critical Path Method (CPM)

Formal Definition

A step-by-step project management technique used to identify activities on the shortest path to completion.

Contextual Application

Delays in any task on the critical path will directly delay the entire project completion date, making it the most vital sequence in site management.

Example in Context

"The project manager noted that the delay in the foundation pour had affected the critical path by four days."

Common Misuse

Confused with 'Milestones'; Milestones are points in time, while the critical path is a sequence of dependent tasks.

Related Terminology

Knowledge Check

What happens if a task on the critical path is delayed?

Is a milestone the same as a critical path task?