estimate to complete

Also written as: ETC

The expected additional cost of an activity, a group of activities, or of the project when the defined scope of work is completed. Most techniques for forecasting EAC include some adjustment of the original cost estimate based on project performance to date. Also shown as "estimated at completion". Often shown as EAC = Actuals-to-date + ETC.

estimate to complete is part of the Actuarial Analytics editor test terminology.